December 2023 Updates

  1. 12/4/23
  2. 12/11/23
  3. 12/18/23
  4. 12/25/23

12423 NCH 5th5th floor
Panel work in north & central electrical rooms
Started installing light fixtures
AV rough in @ hard lids
Linear diffuser in council chambers
Started placing ceiling registers
Coiling doors installed
Paint touch ups
Restroom tile started
Roof drain in council chambers replaced

 

12423 NCH 4th4th floor
Air handler demo completed
Misc. fan room demo
Taping walls and head of wall spraying
Lighting control and overhead power
Priming walls got started
Panel install south electrical room

 




12423 NCH 1st2nd floor
HVAC overhead rough-in
Plumbing wall rough-in
Plumbing waste and vent
Hydronic piping
Wall insulation completed
The second side sheetrock started
Cable tray, overhead conduit

 



12423 NCH 1st 21st floor
Metal stud wall framing
Soffit framing layout
New 6” gas line install and welding
Stock glass for windows